Title: Status Update: Using NMMS for Building SSWG Cases
1Status Update Using NMMS for Building SSWG Cases
- Wes Woitt
- CenterPoint Energy
- 2010 SSWG Chair
2Current Process
- TSP Data
- Some have internal databases to compile data
- Others take previous case and add projects or
corrections as necessary - Incumbent upon each TSP to coordinate and track
what is contained in data sent to ERCOT
3NMMS Process
MOD
TSP Data PMCR
TSP Data PSSE RAW format
Yes
Posted to ERCOT Website
No
ERCOT Using PSSE
Compile Data and Solve
Output PSSE Cases
Case need tuning?
Ready for use in planning studies
PSSE
ERCOT Determines Dispatch Using UPLAN
Topology from NMMS Topology Processor RAW file to
MOD
TSPs Provide Loads and Device Control
Profiles RAW file to MOD
TSPs Provide Future Projects PMCR
4Topology Processor Functionality
- Topology Processor (TP)
- Converts Operations formatto Planning format
(RAW) files - MOD produces (.PRJ Project)
- Converts Bus/breaker to Bus/branch model
- Case Builder (CB)
- Builds time-based models
4
5Whats been done so far?
- IMM work
- ERCOT prepopulated much of the planning related
data in 2009 - TSPs cleaned up over 1000 incorrect Connectivity
Node Groups (CNGs) - Moved incorrect Connectivity Nodes into the
correct CNGs - Worked with ERCOT to correct CNGs and nodes where
TSPs did not have ownership - TSPs cleaned up planning related data (Area s,
Zone s, ckt IDs, etc.) - Submitted SCR 759
- Worked with ERCOT to modify TP
- MOD training in July
- Currently testing new build process using
Topology Processor (TP) and MOD - Identified issues with TP/IMM
6(No Transcript)
7IMM/TP output PSSE v30TSP Combined Issues List
50
- TP is already dated
- SSWG moved to PSSE v31 in May 2009
- New data types and parameters
- PSSE generally puts out a new version annually
- For TP to be able to include new data types or
new parameters, IMM will need to be changed not
just TP
8No Distribution Cap Banks in TP CaseTSP Combined
Issues List 38
- TSPs model distribution cap banks at transmission
buses in PSSE - Allows cap banks to be switched during planning
studies - IMM does not model equipment below transmission
voltage - Hundreds of these cap banks in ERCOT system
- Cannot solve through MOD Device Control Profile
9Distribution Cap banks
10Zero Impedance Lines Created by TP Have 9999 MVA
RatingsTSP Combined Issues List 35
- TSPs model about 250 zero impedance lines which
have real ratings in SSWG cases - See examples
11Zero Impedance Line Ratings
12Zero Impedance Line Ratings
Zero impedance branch 46110 46111 95 Rate A
360 MVA Rate B 440 MVA Rate C 440 MVA
North Belt 138 kV
Non-zero impedance branch 46111 46002
95 Rate A 455 MVA Rate B 478 MVA Rate C 580
MVA
13Associating Loads and Cap Banks with the Correct
CNGTSP Combined Issues List 33 and 34
- It was somewhat of an art to assign nodes to CNGs
to create model that we wanted to see - See example
14Figure 1 Modeling of Cap Banks and Load Taps in
IMMScenario 1
Bus 40002
Ckt. 01
A
D
To Bus 70000
Bus 50000
B
E
G
C
F
Bus 60000
Ckt. 02
Bus 40001
To Bus 80000
Bus 40000
- LEGEND
- Node Switch
AC Line Segment
Series Compensator Breaker - With the current method of modeling, the cap
bank and distribution load are associated with
Bus 40000. To match the topology of our cases,
the cap bank and distribution load should be
associated with Buses 40001 40002,
respectively. With the cap bank and load modeled
as part of multi-section lines off of the main
bus (40000), we are able to switch the lines,
de-energize the cap bank, and roll the load to
another load bus. This is impossible with the
current method, because when the lines are
de-energized, the cap bank and load remain on the
main bus (40000). - See Figure 2 for the resulting PSSE diagram when
the above (current) method of modeling is run
through the Topology Processor. - See Figure 3 for the desired PSSE topology of
the above substation.
15Figure 2 Resulting PSSE Topology Using Scenario
1 Modeling Method
16Figure 4 Modeling of Cap Banks and Load Taps in
IMMScenario 2
Bus 40002
Ckt. 01
A
D
To Bus 70000
Bus 50000
B
E
G
C
F
Bus 60000
Ckt. 02
Bus 40001
To Bus 80000
Bus 40000
- LEGEND
- Node Switch
AC Line Segment
Series Compensator Breaker - With the current method of modeling, the cap
bank and distribution load are associated with
Bus 40000. To match the topology of our cases,
the cap bank and distribution load should be
associated with Buses 40001 40002,
respectively. With the cap bank and load modeled
as part of multi-section lines off of the main
bus (40000), we are able to switch the lines,
de-energize the cap bank, and roll the load to
another load bus. This is impossible with the
current method, because when the lines are
de-energized, the cap bank and load remain on the
main bus (40000). - See Figure 2 for the resulting PSSE diagram when
the above (current) method of modeling is run
through the Topology Processor. - See Figure 3 for the desired PSSE topology of
the above substation.
17Figure 5 Resulting PSSE Topology Using Scenario
2 Modeling Method
18Figure 3 Desired PSSE Topology
19Autotransformer Modeling IssuesTSP Combined
Issues List 41, 42, 48, and 52
- 48 and 52
- CNP reported that the TP was incorrectly
calculating off-nominal 3-winding transformer
impedances. - Subsequent discussion with ERCOT/Siemens leads us
to believe that we are inputting incorrect Ohmic
impedances into IMM Still testing - Siemens has used this method in other regions and
had the same arguments - No documentation about what we are expected to
provide in IMM or what calculation TP is using - 41
- CNP Operations standardizes all autos SCADA
does adjustment automatically - PSSE does not have that same intelligence
therefore, IMM auto models must be adjusted to
reflect real equipment characteristics - Some parameters can be changed in Device Control
Profile, but not all - Not talking about ratings and impedances
differences - 42
- Allow a phase shift to be applied to transformers
and output in the case. Useful when creating
cases for fault duty studies to have this already
in case. - This has nothing to do with phase-shifting
transformers
20Autotransformer Ops Model vs. Planning Model
- The device control profile is not robust enough
to handle the majority of differences between the
Topology Processor output case and the
Transmission Planning case. Instead, at least 50
3-winding transformers in CenterPoint Energys
area will require PRJ files to alter the Topology
Processor output case to a typical Transmission
Planning case. - Differences Resolved with PRJ
- Moving the LTC from the low winding to the high
winding. - Number of taps
- Specifying a different voltage control bus
- The tap range of the LTC Rmax, Rmin
- Differences Resolved with Device Control Profile
- Winding voltage for off-nominal NLTC settings.
- The auto-adjust code for LTC windings
- Voltage control bus regulation values Vmax, Vmin
21FACTS Device ModelingTSP Combined Issues List 32
- PSSE allows modeling FACTS devices (STATCOMs,
SVCs, TSCs, etc.) in a number of different ways - Generator
- Switched shunt
- FACTS Device
- TP only outputs a FACTS device as a generator
model - Important to model correctly for dynamic studies
22FACTS Devices
- Planning Case CNPs FACTS Device
- TP Case model CNPs FACTS Device
23FACTS Devices
- Planning Case AENs FACTS Device
- TP case AENs FACTS Device, currently on wrong
bus
24PSSE IDs for Branches
- PSSE allows any two character CKT ID for any
branch - IMM has validation rules that series devices PSSE
CKT IDs have to be Sx - TP automatically creates PSSE CKT ID of BC or BO
for any branch that represents and breaker or
switch - Would prefer to leave PSSE CKT ID open and left
to the discretion of TSPs
Line IDs with BO/BC ID
25RARF Data TSP Combined Issues List 30
- TSPs have seen lots of basic problems with RARF
data - MBASE
- Zsorce
- Other RARF data problems
- Reactive data does not correspond with biennial
tests - RARFs submitted with erroneous PSSE bus numbers
- ERCOT Network Modeling creates NOMCRs
- Creates problems with TP output as SSWG recently
discovered - Need process to allow TSP review
- Even more issues with wind resource RARFs
- NPRRs currently being drafted or in process
26Equipment Associated with SPS/RAPs Modeled in
IMM TSP Combined Issues List 49
- SPS/RAP models are not real equipment
- TSPs see additional data in TP output
27Remaining Issues TSP Combined Issues List 26,
27, 28, 29
- 26 Each of the items identified above can be
fixed in SSWG base cases through Standard PMCRs
- Taken as a whole, this represents an enormous
amount of corrections to make to the case - SCR being drafted to propose changes to many of
these - 27 Changes described in 26 are not
implemented by next spring - 28 SCR 759 is never implemented
- Multi-section line creation is not functional
- 29 Case building process is still very unclear
- Due to these uncertainties
- Just begun finding issues with MOD
28Remaining Issues TSP Combined Issues List 40,
48, 51, 52
- 40 Specific modeling added for contingency
analysis, dynamic analysis, short circuit
analysis, etc., that is lost by creating cases
from IMM data - This punishes TSPs who have made a concerted
effort to align their base cases to serve the
needs of planning, protection, and stability
studies without having to maintain separate
cases. - 48 Topology Processor issues
- Software is still being changed
- Radial line reduction still not working properly
- 51 Not all TSPs have PSSE which is creating
problems with their ability to create PRJ files - Potential resolution is being discussed, but it
is a workaround - 52 Lack of documentation about TP