Title: Building Optimization and Sustainability
1Building Optimization and Sustainability
- Cameron Symes, P.E.
- Estes, McClure Associates, Inc.
2Summary
- What is sustainable design?
- The sustainable design process
- Tools for sustainable design
- Building optimization and sustainability
3What is Sustainable Design?
4The Process
5The Process
6The Process
- Develop the vision early
- Design Charrette
- Sample goals 50 energy reduction from ASHRAE
90.1, LEED Platinum, use daylighting throughout
and include lighting controls, or all the above
7The Process
- Building Envelope
- Passive Solar Design
- Daylighting Design
- Windows and Glazing
- Insulation
- Natural Ventilation
8The Process
- Optimize site potential
- Optimize energy use
- Protect and Conserve Water
- Use Greener materials
- Enhance IEQ
- Optimize MO
9Tools - Daylighting
10Daylight Factor distribution snapshot of
available daylight inside the building
traditionally during overcast sky
Climate-based daylight metrics provide insight
to daylight quality and site location influence
11Tools Energy Modeling
- The dynamic thermal model of the building should
serve as a basis for decisions from the
beginning throughout the - design process
- Schematic Design
- Reasonable assumptions made regarding internal
gains, occupancy, lighting systems where
necessary - Baseline case developed to provide an eventual
comparative basis for evaluating various design
alternatives - Absolute accuracy is not primary concern as long
as assumptions are consistent between both cases - Evaluate changes to building envelope, glazing
building orientation, fenestrations, and HVAC
system types - Explore daylighting considerations obstruction
shading analysis, solar penetration into
floorplans, window shading features analysis - Example below thermal performance comparison of
different building fabric constructions
Life cycle cost analysis
12Tools Energy Modeling
- Detailed Design
- Building construction and MEP system selections
have been narrowed down but iterations continue
into this phase - Specific building features and systems are
fine-tuned and further evaluated among design
consultants and shareholders - Finalize structural, HVAC, lighting systems
- Modeling assumptions are removed as much as
possible and replaced with best estimates to
constitute Proposed Design - Key design concerns are resolved. Example below
CFD of atrium/common area in school to examine
architects stratification concerns on second
level
13Tools Energy Modeling
- Post-occupancy
- Implementation of building energy model can
continue beyond occupancy to monitor occupants
behavior and impacts on energy usage - Energy model can be developed for optimization of
existing buildings with same approach (ie. ASHRAE
Level audits)
14Tools - Life Cycle Cost Analysis
Where is the money going?
15Building Optimization and Sustainability
If you plan for sustainability, design for
sustainability, and construct for sustainability,
but do not verify sustainability then you have
missed the mark.
HOW????
16Why Optimization?
- We want our buildings to operate as planned
- We want to improve the sustainability of existing
facilities - We want to minimize life cycle costs
We Tune Up Our CarsWhy Not Our Buildings?
17Is Your Building a Candidate for Optimization?
- Increased energy usage
- Comfort complaints
- IAQ issues
- OM problems
- Does not meet sustainability goals
18The Focuses of Optimization
- Mechanical systems
- EMCS
- Daylighting controls
19The Process
- Assessment
- Analyze design intent
- Analyze utility data
- Interview facility personnel
- Conduct building walk-through
- Review controls settings
- Monitoring testing
- Trend data from BAS
- Test balance
- Functional testing
- Condense problems into executable steps
- Implement selected solutions
- Document through final report
20Assessment
- Initial meeting w/ personnel
- Involve all parties
- Identify building problems issues
- List goals objectives of optimization
- Building walk-through
- Perform cursory observations
- Obtain existing drawings
21Functional Testing
- Develop testing plan
- Select equipment to be tested
- Determine expected or correct responses
- Change
- Parameters
- Set points
- Conditions
- Observe responses
- Document deficiencies
22Potential Deficiencies
- Inadequate initial design
- Improper equipment installation
- Lack of maintenance
- Incorrect air flows
- Incorrect chilled/hot water flows
- Improper controls programming/settings
- Faulty equipment or components
23Sample Improvements
- No cost
- Change MO practices
- Low cost
- Replace bad parts components
- Re-program controls
- Re-balance air and/or water flows
- Capital projects
- Equipment replacements
- Controls replacements
24Possible Benefits
- Better occupant comfort
- Improved IAQ
- Reduced energy use
- Fewer maintenance calls
- More efficient equipment operation
- Better systems reliability
25Case Studies
26DeGolyer Elementary
- 45,466 square feet
- Built 1960
- HVAC renovations 2004
- System 4-pipe CHW w/ VAV
27DeGolyer Elementary
- Issues reported
- Inconsistent temperature humidity levels
- Noisy HVAC equipment
- Unreliable HVAC controls
- Problems found
- Excessive air flows
- Non-functioning valves dampers
- Outdated components
28DeGolyer Elementary
- Results
- Reliable systems
- Reduced classroom noise
- Uniform temperatures
- Project details
- Deficiencies discovered 69
- Recommendations for correction 13
- Total cost 162,000
- Projected energy savings 25,000
- Payback 6.5 years
29Gonzalez Elementary
- 90,000 square feet, 2-story
- Built 2006
- HVAC systems RTUs
30Gonzalez Elementary
- Issues reported
- Uncomfortable indoor conditions
- Units uncontrollable through BAS
- Problems found
- Outside air dampers not functioning properly
- EMCS communication problems
- Inoperative RTUs
- Dirty filters coils
31Gonzalez Elementary
- Common controls one component
- Reliable front end graphics
- Safeties installed on RTUs
- Extended equipment life
- Immediate energy savings
- Consistent temperatures
- New startup logs
32Gonzalez Elementary
33Ferguson Junior High
- 128,000 square feet, 2-story
- Built 2000
- HVAC systems
- 4-pipe CHW
- Air-cooled screw chillers
- RTU on gym, computer labs, administration
34Ferguson Junior High
- Issues reported
- Inconsistent temperatures
- High humidity levels
- Unreliable HVAC EMCS
- High utility costs
- Problems found
- Inaccurate sensor readings
- Controls manually over-ridden
- Improper sequences of operation
35Ferguson Junior High
- Recommendations
- Correct sequence of operations
- Replace
- Bad valves
- Sensors
- Controllers
36Summary
- What is sustainable design?
- The sustainable design process
- Tools for sustainable design
- Building optimization and sustainability
37Questions?