Title: JUSTIFICATION AND APPROVAL FOR OTHER THAN FULL AND OPEN COMPETITION Market Research Commerciality De
1JUSTIFICATION AND APPROVALFOR OTHER THAN FULL
AND OPEN COMPETITIONMarket Research/
Commerciality Determination
- Acquisition University
- Presented by
- Competition Management Office
- January 2004
2Course Objectives
- Provide guidance and instruction on how to
prepare quality JAs - Provide guidance and instruction on how to
prepare quality Market Research Report/
Commerciality Determinations (MRR/CD)
3Competition ManagementOur Mission
- Management of a comprehensive competition program
- Responsive cost-effective spare parts acquisition
program - Commercial/Non-developmental Item Program
4Competition Advocate
- Public Law 98-369 Competition in Contracting
Act (CICA), 1984 Each MSC shall have an
Advocate for Competition responsible for
challenging barriers and promoting full and open
competition while challenging specifications and
restrictive need statements. - Public Law 103-355 Federal Acquisition
Streamlining Act (FASA), 1994 Advocates for
Competition shall promote the acquisition of
commercial items and challenge burdensome
contract clauses. - Public Law 104-106 Federal Acquisition Reform
Act (FARA), 1996 shall ensure that the
requirement to obtain full and open competition
is implemented in a manner that is consistent
with the need to efficiently fulfill the
Governments requirements.
5Who We Are
- Mr. Wade Griffin- Manager - Competition Advocate
- Ms. Rebecca Pratcher- Alternate Competition
Advocate - Ms. LaQuandis Baldwin- Clerk
- Mr. Victor Kerns- Alternate Competition Advocate/
General Engineer - Mr. Shelley Muhammad- Logistics Mgmt Specialist
- Ms. Sharon Blackwell- Procurement Analyst
- Mr. Ernie Robinson- Procurement Analyst
- Mr. Russ Hickam- Procurement Analyst
- Ms. Cathy Richardson- Procurement Analyst
- Mr. Harold Jones Procurement Analyst
6Justification and Approvals
- Whos job is it to promote competition?
- When is a JA not required?
- JA format-paragraph by paragraph review/
instruction
7Justification and Approvals(continued)
- What documents need to be included in the JA
file?
- Who is responsible for the JA?
- When is an amended JA required?
- JAs for long-term contracts
8Whos Job Is It to Promote Competition?
- Competition Management
- Contracting Officers
- FAR 6.101
- 10.U.S.C. 2304 and 41 U.S.C. 253 contracting
officers shall promote and provide for full and
open competition - FAR 6.303-1shall not award any other contract
without providing for full and open competition
unless - Justifies in writing
- Certifies justification
- Obtains the required approvals
9When Is a JA Required?
- Any time you contract without providing for full
and open competition based on one of seven
exceptions/circumstances
107 Exceptions to Full Open Competition
- 6.302-1 Only one responsible source
- 6.302-2 Unusual and compelling urgency.
- 6.302-3 Industrial mobilization engineering,
developmental, or research capability or expert
services. - 6.302-4 International agreement.
- 6.302-5 Authorized or required by statute.
- 6.302-6 National security.
- 6.302-7 Public interest.
11When Is a JA Not Required?
- When you have Full and Open Competition
- FAR 6.001
- Contracts awarded using simplified acquisition
procedures - Contracts awarded using contracting procedures
are expressly authorized by statute - Contract modifications, - exercise of priced
options that were evaluated and within the scope
of an existing contract - Orders placed under requirements contracts or
definite-quantity contracts - Orders placed under indefinite-quantity contracts
- Orders placed against task order and delivery
order contracts
12When is a JA Not Required?
- Far 6.200
- Establishing or maintaining alternative sources
- Set-asides for small business concerns
- Section 8(a) competition
- Set-asides for HUB Zone small business concerns
13JA Format
-
- JA Format and Content http//www.redstone.army.m
il/cgi-bin/casl/index.pl - SAMPLE FORMATSee Student Handout
14JA Approval Levels
- 500,000
- 500,001 - 10,000,000
- 10,000,001 -50,000,000
- COs certification
- Competition or the Alternate
- Principal Assistant Responsible for Contracting
(PARC )-Ms. L. Marlene Cruze and AMCOM Deputy
Commander- Mr. James L. Flinn III.
15JA Approval Levels(continued)
- 50,000,000
- Justification Review Document (JRD)
- Approved Acquisition Plan,
- Transmittal memo signed HCA
- Forward electronically as Word document
attachments to Headquarters, Department of the
Army, E-Mail PSStaff_at_saalt.army.mil.
16What Documents Need to Accompany the JA ?
- Technical and Requirements Certification
Procurement History Commerciality Determination
- Statement of Impact (SOI)/ Statement of Urgency
(SOU)
- Justification Review Document (JRD)
- Approved Acquisition Plan
17Urgent JAs
- Urgency exception
- Clearly demonstrate that the United States
Government is or will be injured if immediate
contract action is not taken. - Injury can be monetary or mission impacting
- Must be directly related to your immediate
requirement. - Signed Statement of Urgency or Statement of
Impact required
18Urgent JAs
- CMO logistics management specialist
- Logistics review of asset position
- Determines the quantity justified as urgent.
- A high priority designation alone will not
justify the use of urgency.
- Post-award approval is not automatic.
- Criteria apply in both pre- and post-award
environments
19When Is an Amended JA Required?
- AFARS 5106.303-1-90
- An increase in the dollar value beyond the
authority of the previous approving official - A change in the competitive strategy
- A change in requirements
- The contracting officer shall document any other
significant change in the dollar value in the
contract file. - Prepare amended justifications -6.303-2-90(b)(3).
20Class JAs
- AFARS 5106.303-1
- Contracts to be awarded in successive fiscal
years - The requirements and quantities included in the
Future Years Defense Plan (FYDP) - Costs have been specifically identified.
- Must address every contract (action) in detail
- Must include only those supply or service
components that are, and will clearly remain sole
source - FAR 6.304
- Approved in writing IAW agency procedures
21JAs - Long-Term Contracts
- Recent trends
- JAs for long-term contracts-partnering contracts
for 5-10 years - Lifecycle JAs for LRIP through Production (14
year) - Reasonableness should be exercised
22Long-Term JAs Our Concerns
- Major changes or program revisions
- Competition and breakout will not be reviewed.
- Missed opportunities to expand the vendor base
and save money. - HQ DA may restrict
- FYDP
- 5 years - Natl Def Auth Act of 2004
23Common Deficiencies
- System/program supported not indicated.
- Type of pricing arrangement not indicated.
- Information from the MRR/CD not in JA.
- Synopsis publication date not in JA.
- SOI/SOU is not attached to JA.
- Part number, NSN, Noun, Quantity, System and
total dollar amount is not on the approval page.
- CASL publication date not indicated
- No explanation provided when a past source will
not be solicited.
- JA has not been reviewed by the legal office
prior to being sent to CMO
24Market Research Commerciality Determination
- Why buy Commercial Items?
- When is a MRR/CD required?
- Who does the market research?
- What is the purpose of Market Research and how
much research is enough?
- MRR/ CD format- paragraph by paragraph guidance/
instruction
- MRR/CD for long-term contracts
- Commerciality Determination And Certification
(CDAC) System
25Why Buy Commercial Items?
- It is the law
- Public Law 103-355,
- 1994 FEDERAL ACQUISITION SREAMLINING ACT
- Federal Acquisition Regulation (FAR)
- Implemented fully the commercial item emphasis of
the Federal Acquisition Streamlining Act.
26When Is a MRR/ CD Required?
- Market research conducted and documented
acquisitions or 25,000 - MR 12 months old.
- Commerciality Determination required for
acquisitions - Competitive or noncompetitive
- Materiel or services
27Who Does Market Research?
- AFARS 5110.002(b)
- Program managers
- Requiring activity.
- Requirements personnel and CO(KO) must work
together.
28What Is the Purpose ofMarket Research?
- FAR 10.000
- To arrive at the most suitable approach to
acquiring, distributing, and supporting supplies
and services. - To determine if commercial items or
nondevelopmental items are available to meet the
Government's needs
29MR Results Are Used To
- Determine if sources capable of satisfying the
agency's requirements exist - Determine the practices of firms engaged in
producing, distributing, and supporting
commercial items - Determine whether bundling is necessary and
justified
30How Much MR Is Enough?
- The extent of market research will vary, depends
on - Urgency
- Estimated dollar value
- Complexity
- Past experience
31MRR/ CD Format/ Instruction
- The sample format
- http//www.redstone.army.mil/cgi-bin/casl/index.pl
- See the Student Handout
32MRR/CD for Long-TermContracts
- Can be done for long-term contracts
- Must be current and no more than 12 months old.
- Annual updates to your MRR/CD must be conducted
and processed in order
33Commerciality Determination and Certification
(CDAC) System
- Automated system MRR/CD for spares.
- Review and approval process is paperless
- Commercial items procured
- Requirements not forwarded to the CMO
- A wavier not required
34Common MRR/CD Deficiencies
- Person who conducted the research is not
identified in paragraph 6
- Requirement has not been published in CASL
- The CASL publication date is inaccurate or
omitted.
- Explanation provided in paragraph 8 does not
explain the commerciality decision
- Information in the MRR/CD is not summarized in
the JA or does not agree with information in the
JA.
35Contact Us
- Appendix A - a list of CMO POCs by weapon system.
- If you have a general questions or concerns email
the CMO cmo_at_redstone.army.mil - Walk-ins are still welcomed!