Title: Demand Response
1Demand Response
- A 28 Year History of Demand Response Programs for
the Electric Cooperatives of Arkansas - by
- Forest Kessinger
- Manager, Rates and Forecasting
2Why do Utilities / Consumers Engage in Demand
Response?
- To gain an economic advantage in their bill.
- To avoid a short-term capacity shortage.
- To avoid a long-term capacity investment.
- Thought - In the long-run, if your pricing
signal (rate) encourages demand response,
objective number 3 is met through a reaction to
that pricing signal.
3Currently, AR Cooperatives have Approximately 730
MWs of Demand Response -This is Achieved by
- Direct control by the member cooperatives.
- 2. Voluntary control by a retail consumer using
cooperative supplied instantaneous and hourly
load data. - Direct control of industrial loads by AECC.
- Voltage Reduction during peak periods.
4Arkansas Co-op. Demand Response Quantified
- Controlled by Member Cooperatives 107 MW
- Voluntary Retail Peak Avoidance 80 MW
- Controlled by AECC
550 MW -
- Total Demand Response 737 MW
5Load Controlled by Member Cooperatives 4
CI Voluntary Control 3
Load Controlled by AECC 20
Firm Load 73
Note AECCs 2006 firm load 1,971 MW
6How did Demand Response Begin for the Electric
Cooperatives?
7Category 1Direct Load Control by the Member
Cooperative
8Time-based Metering
- In 1978, Arkansas Electric Cooperative
Corporation (AECC) installed wholesale metering
which recorded hourly kW demand by wholesale
point of delivery. This hourly data could be
processed into simultaneous hourly coincident
totals for wholesale points of delivery for each
member cooperative.
9Coincident Peak Rate Design
- Further, AECCs Board of Directors approved a
wholesale rate design which included billing
demands based on the member cooperatives
contribution to AECCs simultaneous summer
peak(s). Billing demands established during the
peak(s) were charged until the new peak(s) was
set the following summer.
10Cost-of-ServiceCost Allocation Methodology
- At the same time, AECCs Board of Directors
adopted a cost of service approach which placed
its fixed costs in the demand charge while
variable costs flowed through the energy charge
and fuel adder.
11By 1985, AECCs Wholesale Rates were as Follows
- Demand Charge 12.14 / kW / month
- Energy Charge 0.0199 per kWh
12The Short-term Reward for Control
- Needless to say, the reward for controlling peak
was great. If there was potential for a member
cooperative to control its annual peak, a load
control system might economically be justified.
The reward to the member cooperative was a
reduced demand billing for the following year.
13The Long-term Reward for Control
- The long-term reward for controlling peaks is
also great. All (even those who do not have
demand response capabilities) benefit through
AECCs ability to avoid building future peaking
plants.
14Early Target Loads for Demand Response
- Irrigation Water Pumping
- (a) row crop,
- (b) field flooding (rice), and
- (c) catfish farming
- Residential
- (a) air-conditioning, and
- (b) water heating
15Means of Control
- The member cooperatives control 107 MW of peak
demand using approximately 40,000 radio control
switches. - Twelve of Arkansas seventeen member
cooperatives currently engage in direct load
control. -
16Reported Member Load Control
1979 1,962 kW under Control
1985 58,869
1995 153,217
2000 159,285
2004 147,706
All numbers represent reported installed control. Achieved control will always be less. All numbers represent reported installed control. Achieved control will always be less. All numbers represent reported installed control. Achieved control will always be less. All numbers represent reported installed control. Achieved control will always be less. All numbers represent reported installed control. Achieved control will always be less.
17Estimated Achieved Load Control by Cooperative
Craighead 4,382 kW Mississippi 10,817 kW
First 17,235 Ozarks -
Farmers 2,977 North AR 9,219
Southwest - Ouachita -
AR Valley - Petit Jean 2,946
Woodruff 47,490 So. Central 2,838
Carroll 3,846 Ashley-Chicot 4,431
CL 2,254 Rich Mt. -
Clay 1,659
Total 107,117 kW
18(No Transcript)
19(No Transcript)
20(No Transcript)
21(No Transcript)
22(No Transcript)
23Category 2Retail Voluntary Load Control
- In the 1990s, member cooperatives began
offering CI retail members rate designs that
mirrored AECCs wholesale firm rate. - If the retail member avoided AECCs peak, then
the member cooperative passed along its wholesale
savings to the retail consumer.
24Requirements
- A communications system that allows the retail
consumer instantaneous load data so that the
consumer might evaluate potential peak periods. - Time based retail hourly metering so that the
distribution cooperative can confirm that the
retail consumer actually avoided AECCs billing
peaks.
25Participation
- Currently, at least ten member cooperatives
offer some type of voluntary peak avoidance rate
to their retail CI consumers. - There are probably in excess of 29 CI consumers
taking advantage of voluntary peak avoidance
rates. - AECC believes that voluntary control provides at
least 80 MW of peak avoidance.
26(No Transcript)
27(No Transcript)
28Category 3Loads Controlled by AECC
- The retail member must be 5 MW or larger.
- AECC places the load within an assigned block.
- The retail load has three hours notice of
interruption. - ½ of the hours may be interrupted for any reason.
- ½ of the hours may be interrupted only to avoid
the interruption of firm load (for capacity
shortage). - The member cooperative implements AECCs IC Rider
with a retail tariff or special rate contract. - Note Interruptions for any reason will not
begin until 1 Jan 2008.
29Interruptible Load Blocks
Load Limit Maximum Annual Interruption
Block - 12 674,001 kW to 714,000 kW 1,200 hours
Block - 11 574,001 kW to 674,000 kW 993 hours
Block - 10 529,001 kW to 574,000 kW 933 hours
Block - 9 489,001 kW to 529,000 kW 804 hours
Block - 8 444,001 kW to 489,000 kW 724 hours
Block - 7 409,001 kW to 444,000 kW 633 hours
Block - 6 369,001 kW to 409,000 kW 555 hours
Block - 5 329,001 kW to 369,000 kW 481 hours
Block - 4 289,001 kW to 329,000 kW 408 hours
Block - 3 249,001 kW to 289,000 kW 340 hours
Block - 2 209,001 kW to 249,000 kW 274 hours
Block - 1 0 kW to 209,000 kW 200 hours
30Supplemental Service /Buy-through
- While AECC may interrupt a load served under the
IC Rider, AECC and the member cooperative will,
if available, offer supplemental service to
prevent the interruptible load from physically
being interrupted.
31Supplemental Service /Buy-through- Continued -
- When available from the market, AECC will offer
interruptible supplemental service to member
cooperative for their interruptible retail
members. - Supplemental service is offered at an
incremental market price plus a small adder. The
retail member may accept or decline the
supplemental offer. - Interruptions for fuel economics, when combined
with supplemental service, also introduces an
element of critical time pricing. - Note Interruptible supplemental service has a
five minutes interruption notice.
32Category 4Voltage Reduction
- Currently, Southwest Arkansas Electric
Cooperative Corporation is using a voltage
reduction measure to reduce their peak(s) by
approximately one MW. - When Southwests voltage reduction measures are
fully implemented, Southwest estimates that they
will reduce their peak(s) by as much as 5 MW.
33Issues to Consider
- Dont allow the interruptible rate or
interruptible credit to overcompensate the member
cooperative or retail member for peak avoidance. - 2. It is best to interrupt your interruptible
loads.
34AR Public Service CommissionDocket No.
06-004-REnergy Efficiency
- One of the goals of the EERs is Permanent Peak
Demand Reduction.
35Questions ?